As part of a Rapid Build Housing Development for ABM Design & Build, MAHON LTD were awarded the groundworks packages for 43 houses. Works started in June 2020. Under strict COVID-19 restrictions, the project is progressing well. 450m of drainage foul drainage exceeding 3.0m deep, extensive road works for ESB, disposal of over 6000m3 off-site. […]
Tullagh Hill Housing Development
Housing development for KELMIN LTD. 79 housing units on greenfield 8 acre site. Mahon LTD have been awarded full groundworks package including site development, drainage & services and all site finishes. This work is ongoing.
Colaiste Baile Chláir, Claregalway
Ongoing project for ABM Europe. January 2019 – December 2019 Groundworks Contract on two new schools. ETNS steel frame building of 1,700m2 and extension of 2,900m2 to the existing secondary school. Excavation of 9,500m3 of material, on and off-site. Pouring of over 2,000m3 of concrete.