MAHON LTD were sub-contracted by Kelmin Ltd to carry out all site drainage and services works, some over 4.0m deep in granite. All other site services including watermain, ESB, Eir, Siro, street lighting and foul and storm connections were also part of our works. Phase 1 was complete in August 22 with works started on Phase 2 immediately afterwards with a completion date of early 2023.
Bower Hill Housing Development, Athlone
Full groundworks package was awarded to MAHON LTD for 55 units on this site in Athlone, Co. Westmeath. Full package includes site clearance, raft foundations, all drainage and services, road